Engineering Change Management
A complete guide to engineering change management: the ECO/ECN process, the drawing REV system, Title Block fields, PLM & Configuration Management, Deviation vs. Waiver, MRB decisions, and ITAR/EAR export control requirements.
๐ Engineering Change Process โ ECO/ECN
1. Change Request (ECR)
ยท Submitter: engineering / manufacturing / customer
ยท Change description + rationale + impacts
ยท Part number + current Rev
2. Impact Analysis
ยท Affected parts (Where-Used)
ยท Existing inventory โ what to do with it?
ยท Cost + timeline
3. Approval (ECO Board / CCB)
ยท Engineering + manufacturing + purchasing + stores
ยท Effectivity date
4. Implementation
ยท Drawing + Rev update
ยท BOM / requirements update
ยท Notification to all departments (ECN)
5. Closure and Filing
ยท Record in PLM/ERP
ยท Baseline preserved
ยท Submitter: engineering / manufacturing / customer
ยท Change description + rationale + impacts
ยท Part number + current Rev
2. Impact Analysis
ยท Affected parts (Where-Used)
ยท Existing inventory โ what to do with it?
ยท Cost + timeline
3. Approval (ECO Board / CCB)
ยท Engineering + manufacturing + purchasing + stores
ยท Effectivity date
4. Implementation
ยท Drawing + Rev update
ยท BOM / requirements update
ยท Notification to all departments (ECN)
5. Closure and Filing
ยท Record in PLM/ERP
ยท Baseline preserved
ECR โ Engineering Change Request
The entry point to the process: who is requesting, what's the problem (field failure? cost reduction? supplier issue?), proposed solution, impact estimate. The CCB approves/rejects.
ECO โ Engineering Change Order
The binding instruction: what changes + new Rev, Effectivity (S/N/date), disposition of existing inventory (Use-As-Is/Rework/Scrap).
ECN โ Engineering Change Notice
The official distribution to everyone affected โ manufacturing, purchasing, quality, suppliers. Ensures everyone is working from the same version.
๐ Where-Used โ Change Impact Analysis
Before any ECO โ the first question: where else does this part live? A change to a "simple" bolt used in 40 assemblies = 40 required impact checks. A PLM answers this with one click; manual file-based tracking is a recipe for trouble.
๐ค REV System โ Revision Management
| Version | Method | Usage |
|---|---|---|
| A, B, C... | Letters A-Z | ISO/ASME โ very common |
| 0, 1, 2... | Numbers | Some manufacturers |
| P1, P2... | P=Preliminary | Development stage, before approval |
| Rev - | Dash | Initial drawing, pre-REV |
| Rev A | First change | After initial Release |
Don't skip letters! I, O, Q, S, X, Z are avoided (confusion with 1, 0, 0, 5, ร, 2). MIL-STD-100 explicitly prohibits them.
๐ REV Block on a Drawing โ Example
| REV | Description | Date | Approved |
|---|---|---|---|
| A | Changed GD&T on โ12 hole | 01.01.24 | A.L. |
| B | Material change from 6061 to 7075 | 15.03.24 | J.B. |
| C | Added 3ร10mm slot | 01.06.24 | A.L. |
Redline โ Red-Pen Correction
A temporary handwritten mark on a field drawing copy โ until an official update. Only legal with an authorized signature + date + a follow-up ECO opened!
As-Built
The actual final condition โ including approved deviations, material substitutions, and field repairs. Critical for project handover and failure investigations.
Interchangeability โ FFF
Form-Fit-Function: a change that preserves FFF = same part number + new Rev. Breaking FFF = a new part number is mandatory!
๐ Drawing Title Block
| Field | Content | Importance |
|---|---|---|
| Part Number | Unique part number | Critical |
| Part Name | Part name | High |
| Revision | Rev A / B / C | Critical |
| Material | Material + standard | Critical |
| Scale | 1:2 / 1:1 / 2:1 | High |
| Projection | โ First / โ Third | Important |
| General Tolerance | ISO 2768-mK | Important |
| Surface Finish | โN7 (default) | Important |
| Drawn By | Name + date | Medium |
| Approved By | Name + date | Critical |
| Drawing Number | Drawing number | Critical |
The first field checked upon receiving a part: does the drawing Rev match the Rev on the purchase order! A part made perfectly to the wrong Rev = a rejected part.
๐ Drawing Types
| Type | Description |
|---|---|
| Detail Drawing | A single part โ all dimensions and requirements |
| Assembly Drawing | An assembly โ BOM, balloons, assembly relationships |
| Installation Drawing | How the assembly installs into the larger system |
| Tabulated Drawing | A family of similar parts in one table (Dash Numbers) |
๐พ PLM โ Product Lifecycle Management
The system that holds everything in one place: versioned CAD files, BOM, electronic ECO processes, digital signatures. The main benefit: a single source of truth โ no "version sitting on someone's desk".
PDM โ Product Data Management
The vault for CAD files: check-in/out (no overwrites!), automatic versioning, assembly-part relationships. SolidWorks PDM is common.
Full PLM
From idea to end-of-service: requirements, CAD, BOM, ECO, manufacturing, service. Windchill, Teamcenter, 3DEXPERIENCE.
๐ Configuration Management
Baseline โ an approved configuration anchor point. Types: FBL (Functional โ requirements), ABL (Allocated), PBL (Product โ the full manufacturing documentation). Once fixed โ every change goes only through an ECO.
Configuration Audit โ compares: what's documented (Baseline) against what was actually built (As-Built). Mandatory before handing over a critical project.
Configuration Audit โ compares: what's documented (Baseline) against what was actually built (As-Built). Mandatory before handing over a critical project.
Deviation โ pre-approved deviation
"We know we won't meet requirement X โ is that OK?" โ engineering analysis โ approval before production, for a defined batch/quantity.
Example: a hole diameter in raw stock deviates by 0.05mm โ pre-approved because it doesn't affect assembly.
Example: a hole diameter in raw stock deviates by 0.05mm โ pre-approved because it doesn't affect assembly.
Waiver โ after-the-fact approval
"An anomaly came out โ what do we do?" โ MRB reviews โ approval after the part has already been produced non-conforming.
Example: a part already manufactured with a slightly rougher surface finish than required โ MRB checks if it's still functionally acceptable.
Example: a part already manufactured with a slightly rougher surface finish than required โ MRB checks if it's still functionally acceptable.
โ ๏ธ Golden Rules
โข Both documents are limited in quantity/time โ they do not change the official drawing!
โข Full documentation is mandatory โ not a "verbal decision"
โข Repeated/permanent use of the same exception = a red flag โ time to issue a real ECO and update the drawing
โข A Deviation/Waiver living for months without a follow-up ECO = a ticking time bomb of conflicting versions
โข Full documentation is mandatory โ not a "verbal decision"
โข Repeated/permanent use of the same exception = a red flag โ time to issue a real ECO and update the drawing
โข A Deviation/Waiver living for months without a follow-up ECO = a ticking time bomb of conflicting versions
๐ MRB โ Material Review Board
The forum that decides the fate of nonconforming parts โ those not meeting drawing requirements. Composition: engineering + quality (+ customer, on defense/critical programs).
| Decision | Meaning | Requires |
|---|---|---|
| Use-As-Is (UAI) | Good as it is โ despite the nonconformance | Documented engineering justification! |
| Rework | Additional processing to bring it within requirements | Approved process, re-inspection |
| Repair | Fix (not identical to original, but acceptable) | A specially-approved repair process |
| Scrap | Complete rejection | Documentation + destruction/marking |
โ ๏ธ UAI (Use-As-Is) authority โ for authorized personnel only! MRB Crib = a physical holding area for nonconforming parts awaiting a decision, preventing them from accidentally "rolling" into the production line.
๐ ITAR / Export Control Requirements
โธ ITAR: International Traffic in Arms Regulations (USA)
โธ USML: US Munitions List โ controlled items
โธ EAR: Export Administration Regulations (civilian + dual-use)
โธ ECCN: Export Control Classification Number
Drawing marking:
โธ Israel: defense export control โ DECA (SIBAT)
โธ TP-10: export license request forms
โธ USML: US Munitions List โ controlled items
โธ EAR: Export Administration Regulations (civilian + dual-use)
โธ ECCN: Export Control Classification Number
Drawing marking:
WARNING: This document contains technical data
subject to the Export Administration Regulations
(EAR). Export/transfer in violation of EAR
is prohibited. ECCN: 1C002
subject to the Export Administration Regulations
(EAR). Export/transfer in violation of EAR
is prohibited. ECCN: 1C002
โธ Israel: defense export control โ DECA (SIBAT)
โธ TP-10: export license request forms
CAGE Code
A 5-character code identifying a defense supplier worldwide. Appears on drawing title blocks, CoCs, purchase orders. Israel: DSPO. USA: DLIS.
Effectivity + ITAR
An ITAR drawing is an "export" even via email to a foreign national! Access is restricted to US Persons or requires a license. Violation = fines and imprisonment.