Engineering Change Management

A complete guide to engineering change management: the ECO/ECN process, the drawing REV system, Title Block fields, PLM & Configuration Management, Deviation vs. Waiver, MRB decisions, and ITAR/EAR export control requirements.

๐Ÿ“‹ Engineering Change Process โ€” ECO/ECN
1. Change Request (ECR)
  ยท Submitter: engineering / manufacturing / customer
  ยท Change description + rationale + impacts
  ยท Part number + current Rev
2. Impact Analysis
  ยท Affected parts (Where-Used)
  ยท Existing inventory โ€” what to do with it?
  ยท Cost + timeline
3. Approval (ECO Board / CCB)
  ยท Engineering + manufacturing + purchasing + stores
  ยท Effectivity date
4. Implementation
  ยท Drawing + Rev update
  ยท BOM / requirements update
  ยท Notification to all departments (ECN)
5. Closure and Filing
  ยท Record in PLM/ERP
  ยท Baseline preserved
ECR โ€” Engineering Change Request
The entry point to the process: who is requesting, what's the problem (field failure? cost reduction? supplier issue?), proposed solution, impact estimate. The CCB approves/rejects.
ECO โ€” Engineering Change Order
The binding instruction: what changes + new Rev, Effectivity (S/N/date), disposition of existing inventory (Use-As-Is/Rework/Scrap).
ECN โ€” Engineering Change Notice
The official distribution to everyone affected โ€” manufacturing, purchasing, quality, suppliers. Ensures everyone is working from the same version.
๐Ÿ”Ž Where-Used โ€” Change Impact Analysis
Before any ECO โ€” the first question: where else does this part live? A change to a "simple" bolt used in 40 assemblies = 40 required impact checks. A PLM answers this with one click; manual file-based tracking is a recipe for trouble.
๐Ÿ”ค REV System โ€” Revision Management
VersionMethodUsage
A, B, C...Letters A-ZISO/ASME โ€” very common
0, 1, 2...NumbersSome manufacturers
P1, P2...P=PreliminaryDevelopment stage, before approval
Rev -DashInitial drawing, pre-REV
Rev AFirst changeAfter initial Release
Don't skip letters! I, O, Q, S, X, Z are avoided (confusion with 1, 0, 0, 5, ร—, 2). MIL-STD-100 explicitly prohibits them.
๐Ÿ“‹ REV Block on a Drawing โ€” Example
REVDescriptionDateApproved
AChanged GD&T on โŒ€12 hole01.01.24A.L.
BMaterial change from 6061 to 707515.03.24J.B.
CAdded 3ร—10mm slot01.06.24A.L.
Redline โ€” Red-Pen Correction
A temporary handwritten mark on a field drawing copy โ€” until an official update. Only legal with an authorized signature + date + a follow-up ECO opened!
As-Built
The actual final condition โ€” including approved deviations, material substitutions, and field repairs. Critical for project handover and failure investigations.
Interchangeability โ€” FFF
Form-Fit-Function: a change that preserves FFF = same part number + new Rev. Breaking FFF = a new part number is mandatory!
๐Ÿ“ Drawing Title Block
FieldContentImportance
Part NumberUnique part numberCritical
Part NamePart nameHigh
RevisionRev A / B / CCritical
MaterialMaterial + standardCritical
Scale1:2 / 1:1 / 2:1High
ProjectionโŠ• First / โŠ— ThirdImportant
General ToleranceISO 2768-mKImportant
Surface Finishโœ“N7 (default)Important
Drawn ByName + dateMedium
Approved ByName + dateCritical
Drawing NumberDrawing numberCritical
The first field checked upon receiving a part: does the drawing Rev match the Rev on the purchase order! A part made perfectly to the wrong Rev = a rejected part.
๐Ÿ“„ Drawing Types
TypeDescription
Detail DrawingA single part โ€” all dimensions and requirements
Assembly DrawingAn assembly โ€” BOM, balloons, assembly relationships
Installation DrawingHow the assembly installs into the larger system
Tabulated DrawingA family of similar parts in one table (Dash Numbers)
๐Ÿ’พ PLM โ€” Product Lifecycle Management
The system that holds everything in one place: versioned CAD files, BOM, electronic ECO processes, digital signatures. The main benefit: a single source of truth โ€” no "version sitting on someone's desk".
PDM โ€” Product Data Management
The vault for CAD files: check-in/out (no overwrites!), automatic versioning, assembly-part relationships. SolidWorks PDM is common.
Full PLM
From idea to end-of-service: requirements, CAD, BOM, ECO, manufacturing, service. Windchill, Teamcenter, 3DEXPERIENCE.
๐Ÿ“ Configuration Management
Baseline โ€” an approved configuration anchor point. Types: FBL (Functional โ€” requirements), ABL (Allocated), PBL (Product โ€” the full manufacturing documentation). Once fixed โ€” every change goes only through an ECO.

Configuration Audit โ€” compares: what's documented (Baseline) against what was actually built (As-Built). Mandatory before handing over a critical project.
Deviation โ€” pre-approved deviation
"We know we won't meet requirement X โ€” is that OK?" โ†’ engineering analysis โ†’ approval before production, for a defined batch/quantity.

Example: a hole diameter in raw stock deviates by 0.05mm โ€” pre-approved because it doesn't affect assembly.
Waiver โ€” after-the-fact approval
"An anomaly came out โ€” what do we do?" โ†’ MRB reviews โ†’ approval after the part has already been produced non-conforming.

Example: a part already manufactured with a slightly rougher surface finish than required โ€” MRB checks if it's still functionally acceptable.
โš ๏ธ Golden Rules
โ€ข Both documents are limited in quantity/time โ€” they do not change the official drawing!
โ€ข Full documentation is mandatory โ€” not a "verbal decision"
โ€ข Repeated/permanent use of the same exception = a red flag โ€” time to issue a real ECO and update the drawing
โ€ข A Deviation/Waiver living for months without a follow-up ECO = a ticking time bomb of conflicting versions
๐Ÿ” MRB โ€” Material Review Board
The forum that decides the fate of nonconforming parts โ€” those not meeting drawing requirements. Composition: engineering + quality (+ customer, on defense/critical programs).
DecisionMeaningRequires
Use-As-Is (UAI)Good as it is โ€” despite the nonconformanceDocumented engineering justification!
ReworkAdditional processing to bring it within requirementsApproved process, re-inspection
RepairFix (not identical to original, but acceptable)A specially-approved repair process
ScrapComplete rejectionDocumentation + destruction/marking
โš ๏ธ UAI (Use-As-Is) authority โ€” for authorized personnel only! MRB Crib = a physical holding area for nonconforming parts awaiting a decision, preventing them from accidentally "rolling" into the production line.
๐Ÿ”’ ITAR / Export Control Requirements
โ–ธ ITAR: International Traffic in Arms Regulations (USA)
โ–ธ USML: US Munitions List โ€” controlled items
โ–ธ EAR: Export Administration Regulations (civilian + dual-use)
โ–ธ ECCN: Export Control Classification Number

Drawing marking:
WARNING: This document contains technical data
subject to the Export Administration Regulations
(EAR). Export/transfer in violation of EAR
is prohibited. ECCN: 1C002

โ–ธ Israel: defense export control โ€” DECA (SIBAT)
โ–ธ TP-10: export license request forms
CAGE Code
A 5-character code identifying a defense supplier worldwide. Appears on drawing title blocks, CoCs, purchase orders. Israel: DSPO. USA: DLIS.
Effectivity + ITAR
An ITAR drawing is an "export" even via email to a foreign national! Access is restricted to US Persons or requires a license. Violation = fines and imprisonment.