Machining ยท Raw Material ยท Rates ยท BOM ยท Quoting ยท Finishing ยท Inspection ยท Assembly ยท Formulas
๐Ÿงฎ Cost Calculator โ€” Machined Part
How to use: Fill in the 4 cards from top to bottom. The result updates automatically.
Not sure what to enter? Click one of the examples below โ€” the calculator will populate with realistic values for a typical part.
โšก Ready-made examples โ€” click to load:
โš™๏ธ Turning:
โš™๏ธ Milling:
๐Ÿ“ฆ Step 1 โ€” Raw Material
How much material do you need to buy to produce one part? The finished part's weight is multiplied by the waste factor (BTF) โ€” because more material always goes in than remains in the finished part.
Weigh the part or calculate from CAD. Not the raw stock โ€” the finished part!
How many kg of raw stock you need to buy for every kg of finished part. BTF 1.3 = 30% waste.
Approximate price per kg of bar/plate at medium quantity in Israel.
โ€”
โš™๏ธ Step 2 โ€” Machining
How long it takes to set up the machine (Setup) and how long the machine runs on each part. Setup is divided across the whole quantity โ€” the more parts, the lower the setup cost per part.
Machine setup time: fixturing, tool setting, zero setting, first-article run. If there are 2 OPs (setups) โ€” add both together.
How many minutes the machine runs on one part, including all operations (OPs). A simple pin = 2-5 minutes. A complex part = 60-120 minutes.
Machine hour rate including: operator, machine depreciation, electricity, cutting tools, coolant. A more advanced machine = a higher rate.
The larger the quantity, the lower the setup cost per part. 1 part = expensive. 1000 parts = cheap.
โ€”
๐ŸŽจ Step 3 โ€” Finish, Inspection & Extras
Additional costs after machining: coating (anodize, zinc...), heat treatment (hardening), quality inspection, and cleaning/finishing. Not every part needs everything โ€” select only what's relevant.
A protective coating against corrosion/wear. Price per part at medium series.
Hardening, softening, or improving mechanical properties. Required for steels that need hardness.
Measurement, report, CMM. A simple part = basic inspection. Aerospace = full FAI + CMM.
Removing burrs, edge breaking, cleaning. Almost every part requires at least manual deburring.
โ€”
๐Ÿ’ฐ Step 4 โ€” Summary & Price
Overhead = costs not directly tied to the part: rent, electricity, insurance, management, coolant. Typically 25-40%.
Margin = what's left for the shop after all expenses. 15-25% is typical in Israel.
A small shop ~25%. Medium ~30%. Large/aerospace ~35-45%.
Gross margin on the price. 15% = competitive. 20% = reasonable. 25%+ = premium/aerospace.
โ€”
โฑ๏ธ Machine Rates โ€” Israeli Market 2024-2026
Machine Hour Rates โ€” Israel
Price range reflects: shop size, region, workload, urgency
MachineLow โ‚ช/hrAverage โ‚ช/hrHigh โ‚ช/hrSetup โ‚ชNotes
Manual Lathe180250350100โ€“200Individual parts, repairs
CNC Lathe 2-Axis280350450200โ€“500Haas/Doosan/Mazak
CNC Lathe Y+C+Sub380500650400โ€“800Done-In-One
Swiss-Type400550750500โ€“1500Long setup!
VMC 3-Axis300450600200โ€“600Haas VF / Mazak
VMC 5-Axis (3+2)500650850400โ€“1000DMG/Hermle
VMC 5-Axis Sim6508001200600โ€“2000Aerospace, impellers
HMC + Pallet450600800300โ€“800Production series
Surface Grinding250350500150โ€“400Flat surfaces
Cylindrical Grinding300400600200โ€“500OD/ID
Centerless Grinding250350500500โ€“2000High setup, mass production
EDM Wire5007001000300โ€“800By hour or by cut length
EDM Sinker6008001200500โ€“2000+electrode cost
Drill Press12020030050โ€“200Simple holes
Band Saw8015025050โ€“100Cutting raw stock
CNC Bending200350500200โ€“600Amada/Trumpf
Fiber Laser400600900100โ€“300By hour or by meter
Waterjet350500750100โ€“300Any material
โ–ธ Setup = fixed! On a run of 100 โ† Setup/part = marginal. On a run of 1 โ† Setup = 50% of the price
โ–ธ Urgency: ร—1.3โ€“2.0 over the regular rate
โ–ธ Night/weekend: ร—1.25โ€“1.5 premium
โ–ธ Aerospace/defense: ร—1.3โ€“1.5 (documentation + traceability)
Labor Rates
Workโ‚ช/hourNote
Grinding / Deburr120โ€“180Manual
Mechanical Assembly150โ€“250Experienced technician
TIG Welder200โ€“350Aerospace: 350โ€“500
MIG Welder180โ€“280Structural
Quality Control180โ€“300Including CMM
CNC Programming200โ€“400CAM offline
Fixture Design250โ€“450Fixture / Jig
๐Ÿงฑ Raw Material Prices โ€” Israeli Market
Material Price per kg โ€” Israel 2024-2026
Approximate prices, depend on quantity, supplier, period. Bar โŒ€20-100mm
Materialโ‚ช/kgโ‚ช/kg (small)Typical MOQAvailabilityNotes
Steel 1018/10207โ€“1012โ€“186m barโ˜…โ˜…โ˜…โ˜…โ˜…Off the shelf
Steel 104510โ€“1518โ€“256m barโ˜…โ˜…โ˜…โ˜…โ˜…Off the shelf
Steel 414015โ€“2225โ€“356m barโ˜…โ˜…โ˜…โ˜…Common
Steel 434022โ€“3535โ€“503m barโ˜…โ˜…โ˜…Order
12L14 Free-Cut12โ€“1820โ€“306m barโ˜…โ˜…โ˜…โ˜…โ†‘machinability
SS 30340โ€“5560โ€“803m barโ˜…โ˜…โ˜…โ˜…โ†‘machinability vs 304
SS 304/304L45โ€“6065โ€“903m barโ˜…โ˜…โ˜…โ˜…โ˜…Off the shelf
SS 316/316L60โ€“8085โ€“1203m barโ˜…โ˜…โ˜…โ˜…Common
SS 17-4PH100โ€“140150โ€“200Orderโ˜…โ˜…2โ€“4 weeks
Al 6061-T630โ€“4245โ€“653m barโ˜…โ˜…โ˜…โ˜…โ˜…Off the shelf
Al 7075-T650โ€“6570โ€“953m barโ˜…โ˜…โ˜…โ˜…Aerospace
Al 2024-T445โ€“6065โ€“85Orderโ˜…โ˜…โ˜…Aerospace
Ti-6Al-4V Grade 5450โ€“700700โ€“1000Orderโ˜…โ˜…4โ€“8 weeks
Inconel 718900โ€“14001200โ€“2000Orderโ˜…6โ€“12 weeks
Copper C11070โ€“90100โ€“1403m barโ˜…โ˜…โ˜…โ˜…Conductivity
Brass C36070โ€“100110โ€“1503m barโ˜…โ˜…โ˜…โ˜…Free-Cut
POM (Delrin)35โ€“5055โ€“751m barโ˜…โ˜…โ˜…โ˜…Engineering plastic
Nylon PA6630โ€“4550โ€“701m barโ˜…โ˜…โ˜…โ˜…Engineering plastic
PEEK800โ€“12001200โ€“1800Orderโ˜…โ˜…Medical/aerospace
โ–ธ Quantity: price per kg drops 20โ€“40% on an order of 100kg+
โ–ธ Israeli suppliers: Metalux, MLS, Almet, Standard Metals, A.L.M
โ–ธ Material certificate: Mill Cert (3.1) = +โ‚ช5โ€“15/part
Buy-to-Fly โ€” Waste Factor
Part TypeBTFExplanation
Simple shaft / bushing1.1โ€“1.3Minimal waste from bar
Regular turned part1.3โ€“1.5Turning + milling
Complex milled part1.5โ€“2.5Pockets, holes
Structural Aerospace3โ€“8Hog-out from plate
Monolithic Wing Rib10โ€“25!90%+ of material becomes chips
โ–ธ BTF 10 = you buy 10kg, 1kg remains in the part!
โ–ธ Ti-6Al-4V at BTF 10 = raw material = ร—10 the final weight ร—โ‚ช600/kg = very expensive
โ–ธ Near Net Shape: casting/forging โ† BTF 1.5โ€“3 โ† saves material
๐ŸŽจ Coating, Finish & Heat Treatment โ€” Prices
Coatings โ€” Price per Part
Medium part ~100-500cmยฒ. Price per part, not per batch
Coatingโ‚ช/part (series)โ‚ช/part (single)Lead Time
Anodize Type II10โ€“2030โ€“603โ€“5 days
Anodize Type II Dyed15โ€“3040โ€“805โ€“7 days
Anodize Type III (Hard)25โ€“4560โ€“1205โ€“10 days
Zinc Plating10โ€“2025โ€“503โ€“5 days
Electroless Nickel EN20โ€“3550โ€“905โ€“7 days
Hard Chrome30โ€“6080โ€“1507โ€“14 days
Black Oxide8โ€“1520โ€“402โ€“3 days
Alodine (Chem Film)10โ€“2025โ€“503โ€“5 days
Passivation (SS)8โ€“1520โ€“402โ€“5 days
Powder Coat Paint20โ€“4050โ€“1005โ€“7 days
Epoxy Wet Paint30โ€“6070โ€“1505โ€“10 days
Electroless Nickel25โ€“4560โ€“1205โ€“10 days
Cadmium (QQ-P-416)40โ€“80100โ€“20010โ€“21 days
Heat Treatments โ€” Price
Treatmentโ‚ช/part (series)โ‚ช/part (single)Lead Time
Hardening + Tempering (Q&T)15โ€“3040โ€“803โ€“7 days
Carburizing25โ€“5060โ€“1205โ€“10 days
Nitriding30โ€“6070โ€“1507โ€“14 days
Vacuum Hardening40โ€“80100โ€“2005โ€“10 days
Stress Relief10โ€“2025โ€“502โ€“5 days
Annealing10โ€“2025โ€“502โ€“5 days
Induction Hardening20โ€“4050โ€“1003โ€“7 days
Cryogenic Treatment30โ€“6080โ€“1505โ€“10 days
โ–ธ Minimum batch: most heat treaters charge a minimum โ‚ช200โ€“500 per batch
โ–ธ Certificate: a heat treat certificate = +โ‚ช20โ€“50/part
โ–ธ Israeli suppliers: Sherutei Chom, Metam, ITC, Palgei Chom
๐Ÿ” Inspection & Quality โ€” Costs
Mechanical Testing โ€” Prices
Testโ‚ช/testNote
Dimensional Measurement (calipers + micrometer)InternalPart of manufacturing cost
CMM โ€” up to 10 dimensions80โ€“150Per part
CMM โ€” Full FAI (50+ dimensions)200โ€“500AS9102
Surface Roughness Ra20โ€“40Per point
Hardness Test HRC15โ€“30Per point
Micro Hardness Test HV40โ€“80Case depth profile
Tensile Test150โ€“300Specimen + test
Charpy Impact100โ€“2003 specimens minimum
Fatigue Test500โ€“2000Per specimen, run-out
NDT โ€” Non-Destructive Testing
Methodโ‚ช/partโ‚ช/m weldNote
PT (Dye Penetrant)30โ€“6040โ€“80Simple and cheap
MT (Magnetic Particle)30โ€“6040โ€“80Ferromagnetic only
UT (Ultrasonic)60โ€“15080โ€“200Thickness + cracks
RT (Radiographic)150โ€“400200โ€“500Radiation โ€” โ† expensive
PAUT (Phased Array)100โ€“250150โ€“350Replaces RT
He Leak Test100โ€“300โ€”Sealing
Hydro Test80โ€“200โ€”For pressure vessels
โ–ธ NDT for welds: AWS D1.1 = PT minimum, ASME VIII = RT/UT
โ–ธ 100% RT: ร—3โ€“5 the cost vs. Spot (10%) โ€” consider if it's required
โ–ธ PAUT replaces RT: โ†“cost, โ†“time, โ† โ† โ† โ† the trend!
๐Ÿ”ง Assembly & Additional Work โ€” Costs
Assembly โ€” Rates
Workโ‚ช/hourโ‚ช/part (typical)
Simple Mechanical Assembly150โ€“22010โ€“50
Complex Assembly + Calibration200โ€“35050โ€“200
Press-Fit (Bearings, Pins)180โ€“28015โ€“60
Helicoil / Insert Installationโ€”5โ€“15 per unit
Bonding Loctite/Epoxy180โ€“25010โ€“40
Dowel Pin + Reaming200โ€“30020โ€“60
Safety Wiring200โ€“35015โ€“40 per bolt
Balancing (Dynamic)โ€”100โ€“500
Welding โ€” Rates
Typeโ‚ช/hourโ‚ช/m seamNotes
MIG/MAG Steel180โ€“28040โ€“80Structural
TIG SS250โ€“40080โ€“150Piping, vessels
TIG Al250โ€“40080โ€“150AC, โ† โ† difficult
TIG Aerospace (AWS/NADCAP)350โ€“550120โ€“250+documentation
Robot Welding300โ€“45020โ€“50Series โ† โ† โ†“
Laser Welding400โ€“70060โ€“150Precise, โ†“HAZ
Electron Beam600โ€“1200150โ€“400Vacuum, Ti/SS
Additional Services
ServicePriceNotes
Laser Markingโ‚ช5โ€“20/partP/N, S/N, logo
CNC Engravingโ‚ช10โ€“30/partDeep text
Special Packagingโ‚ช10โ€“50/partVCI, desiccant
Masking for Coatingโ‚ช15โ€“50/partThreaded holes, seats
Mill Cert 3.1โ‚ช15โ€“50Material certificate
FAIR / AS9102โ‚ช200โ€“500First article
PPAP Level 3โ‚ช500โ€“2000Automotive โ€” 18 elements
Certificate of Conformanceโ‚ช20โ€“50Basic CoC
๐Ÿ“„ Quotation โ€” Structure and Method
Professional Quote Structure
1. HeaderCompany name, logo, date, quote number, validity
2. Customer DetailsName, contact person, email, RFQ Reference
3. Technical DescriptionP/N, Rev, material, quantity, attached drawing
4. Unit PriceBreakdown: material + machining + finish + inspection
5. NRENon-Recurring: fixture, programming, special tooling
6. Lead TimeBusiness days! FAI + series
7. MOQMinimum quantity + price breaks
8. Payment TermsNet 30/60, deposit?, currency
9. ExclusionsWhat's not included! (coating? NDT? packaging? cert?)
10. SignatureQuote validity (30/60 days), T&C
โ–ธ Price Break: 10/50/100/500 units โ€” with a price reduction
โ–ธ Validity: 30 days standard. Special materials = 14 days
โ–ธ NRE: always separate! The customer pays it once
Lead Time โ€” Typical Delivery Times
StageDays (regular)Days (rush)
Material Order (stock)1โ€“30โ€“1
Material Order (special)14โ€“427โ€“21
CAM Programming1โ€“30.5โ€“1
Machining (simple part)3โ€“51โ€“2
Machining (complex part)7โ€“143โ€“7
Coating5โ€“103โ€“5
Heat Treatment5โ€“103โ€“5
NDT3โ€“71โ€“3
FAI + Report3โ€“51โ€“2
Packaging + Shipping1โ€“20.5โ€“1
โ–ธ Typical total: 3โ€“4 weeks (simple) ยท 6โ€“8 weeks (complex+coating)
โ–ธ Urgency: ร—1.3โ€“2.0 price premium โ€” price it in advance!
๐Ÿ“Š Pricing Formulas & Metrics
Basic Formulas
Material Cost= finished weight ร— BTF ร— โ‚ช/kg
Machining Cost= (Setup/quantity + machine time) ร— rate
Direct Cost= material + machining + finish + inspection
Full Cost= direct cost ร— (1 + overhead%)
Selling Price= full cost ร— (1 + margin%)
NRE= fixture + programming + tooling + first FAI
Break-Even= NRE / (price โˆ’ variable cost)
Performance Metrics โ€” KPIs
OEE= Availability ร— Performance ร— Quality
OEE World Classโ‰ฅ 85%
Scrap Rate= scrap / production quantity. Target: < 2%
On-Time Deliveryโ‰ฅ 95%. < 90% = a problem!
Setup Ratio= setup time / production time. Target: < 15%
Spindle UtilizationSpindle hours / available hours. Target: > 60%
Cost/Part Trendโ†“ with the learning curve โ€” Wright's Law: C_n = Cโ‚ ร— n^b
โ–ธ Learning Curve: 80% LC = every quantity doubling โ† โ†“20% cost
โ–ธ Wright's Law: b = log(LC)/log(2) = log(0.8)/log(2) = โˆ’0.322
Overhead โ€” What Does It Include?
Rent / DepreciationBuilding, machines, equipment
Electricity + WaterCNC = 15โ€“40 kW ร— โ‚ช0.5/kWh
Coolant + OilsReplaced every 3โ€“6 months
Cutting ToolsUsually 5โ€“15% of machining cost
InsuranceFacility + equipment + product liability
AdministrationAccounting, purchasing, management
MaintenancePreventive + corrective + spare parts
Typical Total25โ€“45% of direct cost
โ–ธ Small shop: overhead 25โ€“35%
โ–ธ Medium shop: 30โ€“40%
โ–ธ Large shop + AS9100: 35โ€“50%
โ–ธ Cutting tools: figure 8โ€“12% of the machine hour cost